The October 2021 Wendover Canal Trust work party is in its second week and steady progress is being made. The brick-laying to repair and protect the remains of the old Bridge 4 continues, under temporary shelters to keep off the autumn rain. It should finish next month. The relining from Bridge 4 is approaching the first bend. It has recently crossed an area which until recently contained some of the deepest mud!