The photos below by Steve Bonser, show the great progress throughout 2021, of our restoration from Bridge 4 towards Little Tring. (And we also spent the summer creating the pipe capping/ access road most of the way back to the cart-track entrance.)
The first 8 photos were all taken from Bridge 4 looking towards Little Tring. They show our progress in all weathers, from a hopeless-looking flooded muddy mess in lockdown, to relined canal.

February 2021, flooded in lockdown 
April 1st, pumped out 
April 18th, excavating for pipe capping, bricking 
April 21st, first length of pipe capping, hut moved 
May 10th, more concreting 
September 9th, fully excavated, lined, blocks laid 
Snow on November 29th 
December 13th, lining weighed down with mud
The remaining 4 photos were taken from the other end of the length of canal in the previous photos, looking back towards Bridge 4.

September 6th, lining in far distance 
October 14th, getting closer 
November 18th, note the amount of spoil removed 
December 13th
